Evesham Abbey Bridge and Viaduct
Frequently Asked Questions
Questions
- What is wrong with the existing
structures?
- What is the preferred option?
- What other options have been
considered?
- Why were other options
discounted?
- How much will it cost and who is going to pay
for the project?
- Is the funding from Department for Transport a
certainty?
- What are the main factors in securing
funding?
- How confident are we that bidding will be
successful. When will the DfT make it's decision?
- What happens if the bid is
unsuccessful?
- If funding is secured, when is the construction
work expected to commence?
- When will a contractor be
appointed?
- How long will the project construction
take?
- How long will the bridge be closed to vehicular
traffic?
- What happens to pedestrians and cyclists during
construction?
- Will the contractor be made to make the closure
as short as possible?
- What happens to traffic while the bridge is
closed?
- How will the contractor be
selected?
- Will representatives of the Evesham Community
be involved in selecting the bridge designs?
Answers
- Q. What is wrong with the existing
structures?
A. The structures are suffering corrosion of the reinforcing steels
which is causing a loss in weight carrying capacity
- Q.
What is the preferred option?
A. To replace the existing Bridge and Viaduct with new
structures designed and built to latest standards on the same
alignment as the existing.
- Q. What other options have been considered?
A. Repair and strengthening of the existing, rebuilding on
a different alignment, erecting a temporary bailey bridge off line
and then rebuilding on line.
- Q. Why were other options discounted?
A. Building the new structure away from the current
alignment is more expensive, cause a significant lowering of
capacity to the traffic light controlled junction and will cause a
significant impact of the meadows. The temporary bailey solution is
also a much more expensive scheme.
Repairing does not give a long term robust solution, maintenance
will have to continue and there is the potential of doing it all
again in the medium term future.
- Q. How much will it cost and who
is going to pay for the project?
A. The project is estimated at around £13m. WCC will fund
approximately £4m with the rest coming from a Department for
Transport grant.
- Q. Is the funding from Department for Transport a
certainty?
A. No. The funding request to the Department for Transport
is part of a national funding competition. Schemes from around the
country are bidding for funds. National funding requests amount to
approximately 1.5 times the amount of funding available.
- Q. What are the main factors in securing
funding?
A. Benefits of the project, local support, robust
budgeting, acceptance of risks by the local authority and
deliverability by 2015.
- Q. How confident are we that bidding will be
successful. When will the DfT make it's decision?
A. Indications we have received so far would suggest that
the County Council has put together a very strong bid. The
Department for Transport (DfT) will make a final decision in
December 2011.
- Q. What happens if the bid is unsuccessful?
A. It is unlikely that we would be able to bid for funding
again until after 2015. The County Council will review the options
after the December 2011 decision.
- Q. If funding is secured, when is the
construction work expected to commence?
A. 2013
- Q. When will a contractor be appointed?
A. As soon as DfT confirm funding, a contractor will be
appointed to design, obtain planning permission and rebuild the
structures
- Q. How long will the project construction
take?
A. Completion is expected in 2015
- Q. How long will the bridge be closed to
vehicular traffic?
A. This is dependant on the winning contractor's
programme, but is expected to be about a year.
- Q. What happens to pedestrians and cyclists
during construction?
A. A temporary cycle and footbridge will be provided by
the contractor
- Q. Will the contractor be made to make the
closure as short as possible?
A. The tender is written in a way to encourage the
contractor to deliver the scheme in the shortest time possible as
part of the contract.
- Q. What happens to traffic while the bridge is
closed?
A. A detailed traffic management plan will be implemented
as part of any Bridge closure. More information will be given once
the funding has been secured.
- Q. How will the contractor be selected?
A. There is a defined tender evaluation procedure where
cost, aesthetics, duration of closure and quality of submission are
assessed and scored.
- Q. Will representatives of the Evesham Community
be involved in selecting the bridge designs?
A. Yes. Representatives will form part of a panel to judge
the aesthetics of the designs.
We are not responsible for the content of external sites.
Read more
This page was last reviewed 8 April 2013 at 17:47.
The page is next due for review 5 October 2014.